The issue of providing the population with clean drinking water and covering it with a wastewater system was studied by Yuksalish

 2025-06-09 16:49:24   |     Просмотров: 3814

In the context of global climate change, Uzbekistan has implemented large-scale investment programmes to ensure access to clean drinking water, promote the efficient use of water resources and conserve this valuable natural asset.

Consequently, access to drinking water for the population increased from 63.7% in 2017 to 81% in 2024. Over 9,000 kilometres of drinking water networks were repaired or upgraded during this period, and the number of drinking water production facilities increased to 10,992 by the end of 2024. For the first time, 9 million people gained access to clean drinking water between 2017 and 2024.

At the end of 2024, the Yuksalish Movement conducted public monitoring to evaluate the achievement of planned objectives concerning the provision of clean drinking water and wastewater services to the population.

For reference: According to Paragraph 94 of the Presidential Decree of the Republic of Uzbekistan dated 21 February 2024, 'On the State Programme for the Implementation of the "Uzbekistan – 2030" Strategy in the Year of Supporting Youth and Business', 1.3 trillion soums are to be allocated from the state budget for the implementation of 79 projects. These initiatives include the construction of 1,100 kilometres of water supply networks and 64 facilities across more than 200 neighbourhoods. The aim is to increase the proportion of the population with access to centralised drinking water to 81%, providing clean drinking water to an additional 1.3 million people and improving the water supply for a further 3 million citizens.

As part of the monitoring process, 99 projects scheduled for implementation in 101 neighbourhoods across the country, funded by the state budget, local budgets and international financial institutions, were selected for review through a competitive process. Public opinion on access to drinking water and wastewater services was also assessed.

The findings revealed significant discrepancies between official reports and the reality on the ground: in 23 projects that were officially reported as fully completed and operational, construction, reconstruction and repair work had not actually been finalized; 28 projects had not been commissioned within the designated timeframe; in 15 neighbourhoods, construction was completed but water supply services were not fully operational; in nine projects, the work was found to be substandard.

I. As part of the monitoring process, JSC 'O‘zsuvtaʼminot' officially reported that construction, reconstruction and repair works, as well as network installation for drinking water and wastewater infrastructure, had been fully completed and commissioned at 67 of the 99 reviewed sites. Construction and repair activities were still ongoing at the remaining 32 sites.

However, further investigation revealed that, of the 67 projects reported as completed and operational, the planned works outlined within the project scope had not been fully executed in 23 of them.

For example, construction works had not been completed as planned in the 'Ergashobod' and 'Olaqanot' neighbourhoods (MFY) of the Asaka district and the 'Bobochek' neighbourhood of the Shahrixon district.

II. In 28 neighbourhoods, project facilities were either not commissioned within the established deadlines, or were officially put into operation before construction works were fully completed.

For instance, installation works for the wastewater system of the newly constructed multi-storey buildings on “Farovon” Street in the “Yangi O‘zbekiston” residential complex in the Chust district of the Namangan region were not completed.

Similarly, in the 'Al-Khwarizmi' residential complex in Urgench, Khorezm Region, the installation of the wastewater pipeline and construction of the wastewater facility were left unfinished yet residential units were handed over.

In the “Baxt”, “Istiqlol” and “Ahillik” neighbourhoods of Gulistan city in the Sirdaryo region, the construction of wastewater networks was completed and formally commissioned, yet the wastewater systems themselves were not put into operation.

III. Poor-quality construction, repair, reconstruction and pipeline installation work was carried out in nine neighbourhoods.

For example, in the 'Ulug'bek' and 'Kaliya' neighbourhoods (MFYs) of Jizzakh city in the Jizzakh region, the metal coating of the installed water towers was made from substandard materials and the bases of the towers were found to be disproportionately small, meaning they do not comply with safety standards. In the 'Gulzor' neighbourhood of the Chust district in the Namangan region, the poorly constructed wastewater system in a newly built multi-storey residential building has led to unpleasant odours and technical malfunctions. In the Kattakurgan district of the Samarkand region, a 20-kilometre wastewater network was found to have been constructed late and in violation of technical standards.

IV. In 15 neighbourhoods, construction and repair work under the respective projects had been completed, but the provision of drinking water and wastewater services was either not fully operational or subject to frequent disruption.

For instance, in the 'Zarafshon' neighbourhood (MFY) of the Arnasoy district in the Jizzakh region, a water facility was constructed in 2024 and drinking water was supplied to seven multi-storey buildings containing a total of 70 apartments, housing around 500 residents. However, it was found that drinking water is supplied only once every three days for just 30 minutes, and in seven two-storey buildings, water does not reach the second floor. Similarly, in three streets of the 'Dehibaland' neighbourhood in the Nurota district of the Navoi region, as well as in the 'M. Ulug‘bek', 'Nurafshon', 'Yangi Hayot' and 'Lutfikor' neighbourhoods of the Mirzaobod district of the Sirdaryo region, water is provided only during specific hours of the day.

V. The implementation and oversight of programs aimed at providing drinking water to neighborhoods have not been adequately organized by the responsible authorities.

Specifically, during the monitoring process, when detailed, location-specific data on the target indicators outlined in the annexes to the Presidential Decree of the Republic of Uzbekistan dated September 26, 2020, “On Measures to Further Improve Drinking Water Supply and Wastewater Systems and Enhance the Effectiveness of Investment Projects in the Sector” were requested, it was revealed that no such reporting had been maintained by the relevant enterprise. Furthermore, it was noted that the projects were being implemented under separate programs not aligned with the decree’s framework.

Direct interviews with residents of all neighbourhoods included in the monitoring process revealed that the above issues have caused considerable concern among the population.

Based on the findings of the public monitoring process, the following recommendations are proposed to address and prevent the identified problems:

- Provide training for technical engineers assigned to water supply projects in each district on construction norms and regulations, specifically QMQ 2.04.02-19 'Water Supply. External Networks and Facilities”.

- Ensure the participation of technical specialists from 'Suv taʼminot' JSC and representatives of civil society in the commissioning process of drinking water and wastewater infrastructure.

- Introduce a transparent reporting system for responsible organisations to publicly track the implementation progress of drinking water and wastewater projects.

- Use planning and monitoring software systems that guarantee comprehensive coverage of all households during the project development phase and ensure precise geographic targeting.

- Draw on international best practices to incorporate modern technologies into upcoming projects.

Access to clean drinking water is a fundamental human right and a cornerstone of a dignified life. The Yuksalish Movement urges the public, relevant authorities and citizens to collaborate in addressing the identified challenges, upholding impartial oversight and moving collectively towards effective reforms.